Project description

Adjustment of several production lines to minimum conditions based on an audit.

Scope of work
  • Conducting an audit and creating a report
  • Designing and creating covers for devices that required it
  • Mechanical modernization of devices
  • Installation of light curtains
  • Installation of a high-speed roller shutter
  • Modernization of the security system
  • Update of electrical diagrams